Precautions for bricklayer acceptance

1. The bricks facing the door are full bricks.

Brick requirements, the first posted wall tiles, such as a bath or shower place requires brush waterproof 1.8 meters high. Waterproof coating on the floor, leaving 30cm on the wall to be painted together with the ground. When applying waterproof paint, waterproof marble is required.

2. The waterproof coating is done well. It must be closed for 48 hours and the average water level should not be less than 2 cm.

3. Then tile the floor tiles, the bottom wall tiles and other floor tiles dry after the shop.

4. The bricks must be horizontally and vertically lined, and the required angle must not be violent porcelain. The yin and yang angles must reach 90 degrees. The wall tiles cannot exceed 3% of the emptying rate. The overall flatness requirement does not exceed 2 MM, and the vertical cannot exceed. 3 MM.

5. Seamless wall tiles require the same 1-2MM gap.

6. The slope of the floor tile to the floor drain is 3 slopes.

7. The kitchen floor tiles are applied by the wet method and the polished tiles are applied by the dry method. The flats can be checked with coins.

Tile paving floor inspection wall construction coating marble

Solar Water Heater

Weifang Meltway Co., Ltd. , http://www.wfsnowmelting.com